欧美精品在线第一页,久久av影院,午夜视频在线播放一三,久久91精品久久久久久秒播,成人一区三区,久久综合狠狠综合久久狠狠色综合,成人av一区二区亚洲精,欧美a级在线观看
         
        Feature: Construction site of China-Laos railway as busy as ever during Spring Festival
                         Source: Xinhua | 2019-02-04 11:44:49 | Editor: huaxia

        Constructors work at the site of the first cast-in-place continuous beam of the China-Laos railway at the under-construction Nathon Station Double-track Super Major Bridge, some 360 km north of Vientiane, capital of Laos, Jan. 18, 2019. (Xinhua/Huang Zongwen)

        by Zhang Jianhua, Wang Shan, Huang Zongwen

        VIENTIANE, Feb. 3 (Xinhua) -- All the key projects along the China-Laos railway are set to be completed specifically on exact dates, such as those of the tunnels to be bored through, bridges' closure and concrete casting of substructures.

        "This is the way the project construction is pushed forward, because we can only start the next step after the preceding work is done," Xiao Qianwen, the Communist Party of China (CPC) secretary of joint working committee of the China-Laos railway, told Xinhua on Sunday while inspecting the project.

        The traditional Chinese Lunar New Year, or Spring Festival, falls on Feb. 5 this year in the dry season of Laos, when is the most favorable period for construction.

        "Most of the Chinese workers and engineers have to give up vacation and stay at the construction sites. The Chinese staff can be busier during the Spring Festival than usual, since the construction of the outstanding project under the Belt and Road Initiative is entering the critical and decisive phase in 2019," Xiao said.

        According to Xiao, the joint venture of Laos-China Railway Co., Ltd., which is responsible for the construction and operation of the railway, will adopt a high standard and ensure high quality construction of the railway, to fully realize the target and fulfill the responsibilities entrusted by the peoples and leaders of the two countries.

        "We have completed the 100th T-shape concrete beam today," Hu Bin, manager of the China Railway No.2 Engineering Group (CREC-2) Vientiane beam fabrication yard, told Xinhua. Thus, the yard has achieved one progress, out of the 50 marked in the timetable.

        However, the manager could not let out a sigh of relief. "In the coming days of the Spring Festival, we are to erect the beams of the longest-ever bridge of the railway and the Laos, the Nam Khone super major railway bridge in the north of Lao capital Vientiane," he said.

        The CREC-2 beam yard lies at the southern end of the China-Laos railway. The yard has set a record that it started construction in last February, cast the first beam in June and erected the first railway beam in December in the same year.

        At the northern end of the railway, which is bordering China, the Chinese railway engineering companies are also as busy as bees.

        The Chinese workers and engineers chose to produce joys and make new year wishes with their Lao colleagues at their off-work time.

        Workers from ChinaRailway No. 5 Engineering Group (CREC 5) celebrate the completing of the first over-1000-meter tunnel along the China-Laos railway in Luang Namtha province, Laos, on Oct. 28, 2018. (Xinhua/China Railway No. 5 Engineering Group)

        Prior to the festival at the CREC-5 project camp in Boten, or the China Railway International's construction site of the future Muangxay Railway Station, Chinese staff can be seen, together with their Lao partners, decorating their dorms and offices. They hung red lanterns, New Year blessing slogans and New Year couplets, which symbolize the traditional Chinese culture.

        The Chinese will send a camp video to their families to assure their loved ones feeling the atmosphere of the New Year abroad. The Lao staff will also share the Chinese New Year fun with their families and friends through cellphone videos.

        The middle section of the China-Laos railway runs through tropical forests. The CREC-8 has done a great job there last year when it planted all the piers of the two cross-Mekong bridges.

        The CREC-8's No.2 subsection is constructing a length of 18.125 km railway, with 17.777-km tunnels, completely in an uninhabited area. Till February, the subsection has bored 11.186 km of tunnel, or 63 percent of the total drilling.

        "We've overcome the hardships at the early stage with almost no entrance to the construction sites, but it's not the time to relax," Wu Zhibin, the CPC secretary at the subsection told Xinhua. "I've been in the project for two Spring Festivals, and I will be here during this festival too," he said.

        Wu said in his first Spring Festival spent there in the mountains, the Lao staff were curious about the way the Chinese workers celebrate, but now all of them join the celebration and enjoy the festive atmosphere.

        "I feel the project has been filled with something new and something familiar. The sense of unity and happiness might be the characteristics of the Spring Festival along the China-Laos railway," the subsection manager Yuan Rong said.

        The construction of Ban Muang No. 2 tunnel, one of the key node of the railway in northern Laos' Luang Prabang province, is full of risks and difficulties. The construction is at the critical stage during the Spring Festival and many Chinese workers remain at the site.

        "The cellphone couldn't do so much good at that time and I could only use it to make some expensive phone calls. Now it's fine. I can talk with my wife and kids," said Hu Hongbing, who has joined the CREC-8's tunnel boring team in China and abroad for over 10 years.

        The first thing, the same as his other Chinese peers after coming out of the under-construction tunnel, is picking up his mobile phone.

        Hu said no matter how exhausted he was he felt the warmth after hearing his family's voices and kids' laughters.

        Chinese workers cast concrete at the site of the first cast-in-place continuous beam of the China-Laos railway at the under-construction Nathon Station Double-track Super Major Bridge, some 360 km north of Vientiane, capital of Laos, on Jan. 19, 2019. (Xinhua/Huang Zongwen)

        Aluogebu, an ethnic worker from western China's Sichuan province, is building a tunnel with CREC-5 in the northern Lao border town of Boten.

        "The Chengdu-Kunming Railway changed my hometown, and I know what a railway means. I deeply felt the aspiration of the Lao people to the railway, just like my hometown fellows were looking forward to the railway," he told Xinhua.

        "So, I don't go home this Spring Festival, but stay at the construction site, try to dig through the Boten railway tunnel and complete the railway construction as soon as possible, so as to make the Lao people take their own train and enjoy the benefits of the railway earlier," he said.

        Liang Jingyu, one of the hundreds of Chinese engineers working at the railway construction sites, told Xinhua that this year is the 10th Spring Festival he had been on duty.

        "Construction of a railway will make more people go home easier," Liang said.

        The China-Laos railway is promoted by leaders of the two countries as one of the interconnectivity projects under the China-proposed Belt and Road Initiative.

        Tunnels, bridges and roadbeds have been built along the route after construction of the cross-border railway began in December 2016. It is expected to be operational in December 2021.

        The 414-km China-Laos railway runs from Mohan-Boten border gate in northern Laos to the capital of Vientiane with an operating speed of 160 km per hour.

        Back to Top Close
        Xinhuanet

        Feature: Construction site of China-Laos railway as busy as ever during Spring Festival

        Source: Xinhua 2019-02-04 11:44:49

        Constructors work at the site of the first cast-in-place continuous beam of the China-Laos railway at the under-construction Nathon Station Double-track Super Major Bridge, some 360 km north of Vientiane, capital of Laos, Jan. 18, 2019. (Xinhua/Huang Zongwen)

        by Zhang Jianhua, Wang Shan, Huang Zongwen

        VIENTIANE, Feb. 3 (Xinhua) -- All the key projects along the China-Laos railway are set to be completed specifically on exact dates, such as those of the tunnels to be bored through, bridges' closure and concrete casting of substructures.

        "This is the way the project construction is pushed forward, because we can only start the next step after the preceding work is done," Xiao Qianwen, the Communist Party of China (CPC) secretary of joint working committee of the China-Laos railway, told Xinhua on Sunday while inspecting the project.

        The traditional Chinese Lunar New Year, or Spring Festival, falls on Feb. 5 this year in the dry season of Laos, when is the most favorable period for construction.

        "Most of the Chinese workers and engineers have to give up vacation and stay at the construction sites. The Chinese staff can be busier during the Spring Festival than usual, since the construction of the outstanding project under the Belt and Road Initiative is entering the critical and decisive phase in 2019," Xiao said.

        According to Xiao, the joint venture of Laos-China Railway Co., Ltd., which is responsible for the construction and operation of the railway, will adopt a high standard and ensure high quality construction of the railway, to fully realize the target and fulfill the responsibilities entrusted by the peoples and leaders of the two countries.

        "We have completed the 100th T-shape concrete beam today," Hu Bin, manager of the China Railway No.2 Engineering Group (CREC-2) Vientiane beam fabrication yard, told Xinhua. Thus, the yard has achieved one progress, out of the 50 marked in the timetable.

        However, the manager could not let out a sigh of relief. "In the coming days of the Spring Festival, we are to erect the beams of the longest-ever bridge of the railway and the Laos, the Nam Khone super major railway bridge in the north of Lao capital Vientiane," he said.

        The CREC-2 beam yard lies at the southern end of the China-Laos railway. The yard has set a record that it started construction in last February, cast the first beam in June and erected the first railway beam in December in the same year.

        At the northern end of the railway, which is bordering China, the Chinese railway engineering companies are also as busy as bees.

        The Chinese workers and engineers chose to produce joys and make new year wishes with their Lao colleagues at their off-work time.

        Workers from ChinaRailway No. 5 Engineering Group (CREC 5) celebrate the completing of the first over-1000-meter tunnel along the China-Laos railway in Luang Namtha province, Laos, on Oct. 28, 2018. (Xinhua/China Railway No. 5 Engineering Group)

        Prior to the festival at the CREC-5 project camp in Boten, or the China Railway International's construction site of the future Muangxay Railway Station, Chinese staff can be seen, together with their Lao partners, decorating their dorms and offices. They hung red lanterns, New Year blessing slogans and New Year couplets, which symbolize the traditional Chinese culture.

        The Chinese will send a camp video to their families to assure their loved ones feeling the atmosphere of the New Year abroad. The Lao staff will also share the Chinese New Year fun with their families and friends through cellphone videos.

        The middle section of the China-Laos railway runs through tropical forests. The CREC-8 has done a great job there last year when it planted all the piers of the two cross-Mekong bridges.

        The CREC-8's No.2 subsection is constructing a length of 18.125 km railway, with 17.777-km tunnels, completely in an uninhabited area. Till February, the subsection has bored 11.186 km of tunnel, or 63 percent of the total drilling.

        "We've overcome the hardships at the early stage with almost no entrance to the construction sites, but it's not the time to relax," Wu Zhibin, the CPC secretary at the subsection told Xinhua. "I've been in the project for two Spring Festivals, and I will be here during this festival too," he said.

        Wu said in his first Spring Festival spent there in the mountains, the Lao staff were curious about the way the Chinese workers celebrate, but now all of them join the celebration and enjoy the festive atmosphere.

        "I feel the project has been filled with something new and something familiar. The sense of unity and happiness might be the characteristics of the Spring Festival along the China-Laos railway," the subsection manager Yuan Rong said.

        The construction of Ban Muang No. 2 tunnel, one of the key node of the railway in northern Laos' Luang Prabang province, is full of risks and difficulties. The construction is at the critical stage during the Spring Festival and many Chinese workers remain at the site.

        "The cellphone couldn't do so much good at that time and I could only use it to make some expensive phone calls. Now it's fine. I can talk with my wife and kids," said Hu Hongbing, who has joined the CREC-8's tunnel boring team in China and abroad for over 10 years.

        The first thing, the same as his other Chinese peers after coming out of the under-construction tunnel, is picking up his mobile phone.

        Hu said no matter how exhausted he was he felt the warmth after hearing his family's voices and kids' laughters.

        Chinese workers cast concrete at the site of the first cast-in-place continuous beam of the China-Laos railway at the under-construction Nathon Station Double-track Super Major Bridge, some 360 km north of Vientiane, capital of Laos, on Jan. 19, 2019. (Xinhua/Huang Zongwen)

        Aluogebu, an ethnic worker from western China's Sichuan province, is building a tunnel with CREC-5 in the northern Lao border town of Boten.

        "The Chengdu-Kunming Railway changed my hometown, and I know what a railway means. I deeply felt the aspiration of the Lao people to the railway, just like my hometown fellows were looking forward to the railway," he told Xinhua.

        "So, I don't go home this Spring Festival, but stay at the construction site, try to dig through the Boten railway tunnel and complete the railway construction as soon as possible, so as to make the Lao people take their own train and enjoy the benefits of the railway earlier," he said.

        Liang Jingyu, one of the hundreds of Chinese engineers working at the railway construction sites, told Xinhua that this year is the 10th Spring Festival he had been on duty.

        "Construction of a railway will make more people go home easier," Liang said.

        The China-Laos railway is promoted by leaders of the two countries as one of the interconnectivity projects under the China-proposed Belt and Road Initiative.

        Tunnels, bridges and roadbeds have been built along the route after construction of the cross-border railway began in December 2016. It is expected to be operational in December 2021.

        The 414-km China-Laos railway runs from Mohan-Boten border gate in northern Laos to the capital of Vientiane with an operating speed of 160 km per hour.

        010020070750000000000000011103261377984841
        主站蜘蛛池模板: 午夜wwww| 少妇太爽了在线观看免费| 久久国产精品视频一区| 99国产午夜精品一区二区天美| 91精品黄色| 欧美色综合天天久久| 亚洲激情中文字幕| 国产伦理一区| 欧美亚洲精品suv一区| 国产一区精品在线观看| 亚洲精品国产一区二| 欧美极品少妇videossex| 日本黄页在线观看| 国产精品一区二区在线观看 | 中文字幕在线乱码不卡二区区| 欧美日韩国产精品一区二区| 亚洲一二三在线| 欧美极品少妇| 一级午夜影院| 午夜影院h| **毛片免费| 国产乱一乱二乱三| 国产午夜精品免费一区二区三区视频| 天摸夜夜添久久精品亚洲人成 | 国产乱xxxxx国语对白| 免费看片一区二区三区| 日韩久久电影| 狠狠色噜噜狠狠狠狠色综合久老司机| 日本一区二区电影在线观看| 欧美日韩国产专区| 99久久精品国产国产毛片小说| 欧美在线免费观看一区| 高清欧美xxxx| 久久精品综合| 国产视频精品一区二区三区| 中文字幕日韩一区二区| 国产美女一区二区三区在线观看| 91国内精品白嫩初高生| www.日本一区| 久久国产精品免费视频| 国产偷亚洲偷欧美偷精品| 日本道欧美一区二区aaaa| 亚洲精品456在线播放| 国产区一二| 99久久精品一区| 99久久婷婷国产综合精品草原| 国产99久久九九精品免费| 日本边做饭边被躁bd在线看| 综合久久激情| 蜜臀久久精品久久久用户群体| 国产精品天堂| 狠狠色成色综合网| 欧美人妖一区二区三区| 国产超碰人人模人人爽人人添| 91精品福利在线| 91久久国产露脸精品国产| 精品国产乱码久久久久久虫虫| 日韩区欧美久久久无人区| 国产精品自拍在线观看| 国产一级精品在线观看| 99爱精品在线| 精品国产一区在线| 欧美日韩激情在线| 综合国产一区| 狠狠躁夜夜| 国产精品国产三级国产专区51区| 国产精品国产三级国产播12软件| 国产精一区二区三区| 亚洲精品卡一卡二 | ass韩国白嫩pics| 欧洲激情一区二区| 国产精品视频久久久久久久 | www.久久精品视频| 国产一区欧美一区| 欧美激情国产一区| 国产不卡一区在线| 国产在线一卡| 国产午夜精品一区二区三区最新电影 | 福利电影一区二区三区| 国产精品久久久久久久四虎电影| 日韩夜精品精品免费观看| 欧美乱码精品一区二区三| 一区二区在线精品| 97久久精品人人澡人人爽| 久久久久久久久久国产精品| 国产精品伦一区二区三区级视频频 | 99精品久久99久久久久| 激情欧美一区二区三区| 国产亚洲欧美日韩电影网| 久久一区二区视频| 精品国产91久久久| 狠狠色丁香久久综合频道| 欧美一区二区色| 91精品国产91热久久久做人人| 国产精品久久久久久久久久久杏吧| 亚洲欧美色图在线| 思思久久96热在精品国产| 亚洲精品国产主播一区| 精品特级毛片| 91热精品| 午夜免费网址| 亚欧精品在线观看| 亚洲午夜久久久久久久久电影院| 小萝莉av| 国产一区二区三区大片| 久久精品—区二区三区| 日本黄页在线观看| 色综合久久综合| 一本色道久久综合亚洲精品浪潮| 国产精品不卡在线| 亚洲制服丝袜中文字幕| 91精品国产高清一二三四区| 午夜毛片电影| 久久噜噜少妇网站| 99久久国产综合精品女不卡| 久久艹国产精品| 99riav3国产精品视频| 少妇**毛片| 国产一区三区四区| 欧美精品xxxxx| 91精品夜夜| 午夜影院一区| 国产一区二区中文字幕| 久久午夜鲁丝片午夜精品| 国产一区激情| 好吊妞国产欧美日韩软件大全| 亚洲乱视频| 99日韩精品视频| 国产精品一二二区| 国产偷亚洲偷欧美偷精品 | 精品国产仑片一区二区三区| 日本精品视频一区二区三区| 欧美一区二区三区久久综合| 97人人模人人爽视频一区二区| 狠狠色狠狠色综合婷婷tag| 国产精品午夜一区二区| 日韩av视屏在线观看 | 国产精品一区二区麻豆| 久久国产精品二区| 欧美日韩一二三四区| 日韩不卡毛片| 久久精品99国产精品亚洲最刺激 | 国产第一区二区三区| 国产一区二区麻豆| 国产视频一区二区三区四区| 午夜亚洲国产理论片一二三四| 在线国产二区| 午夜黄色网址| 久久激情综合网| 久久一区二区精品| 夜夜爽av福利精品导航| 午夜色大片| 久久国产精品久久| 日韩欧美一区精品| 日本午夜影视| 国产精品免费一视频区二区三区| 亚洲精品suv精品一区二区| 一级黄色片免费网站| 精品国产一二区| 国产一a在一片一级在一片| 女人被爽到高潮呻吟免费看| 免费午夜在线视频| 欧美久久精品一级c片| 国产精品色在线网站| 欧美精品久久一区| 狠狠躁夜夜躁| 国产精品对白刺激在线观看| 国产免费一区二区三区网站免费| 欧美一区久久| 国v精品久久久网| 日本一二区视频| 亚洲激情中文字幕| 亚洲欧美一二三| 欧美日韩偷拍一区| 国产全肉乱妇杂乱视频在线观看| 欧美色图视频一区| 精品国产乱码久久久久久久久| 高清国产一区二区三区| 性色av香蕉一区二区| 国产精品日韩精品欧美精品| 午夜黄色一级电影| 国产真实一区二区三区| 男女午夜影院| 国产欧美一区二区精品性| 国产一区二区三区小说 | 中文乱码在线视频| 久久国产激情视频| 日韩女女同一区二区三区| 亚洲午夜精品一区二区三区| xxxx18日本护士高清hd| 日韩av在线播放观看| 狠狠色噜噜狠狠狠狠视频| 亚洲精品色婷婷| 午夜特级片| 国产午夜一区二区三区| 国产精品一区二区免费视频| 日韩精品中文字幕在线播放| 少妇av一区二区三区| 日本高清h色视频在线观看| 国产人澡人澡澡澡人碰视| 国产一区二区四区| 91精品啪在线观看国产线免费| 国产精品1区2区| 午夜特片网| 亚洲视频精品一区| 97久久国产亚洲精品超碰热| 久久国产精品-国产精品| 日韩精品久久久久久久的张开腿让| 色婷婷精品久久二区二区蜜臂av| 中文字幕一区二区三区乱码| 制服丝袜二区| 亚洲欧美国产一区二区三区| 夜色av网| 国产不卡一区在线| 精品视频久| 91精品啪在线观看国产线免费| 午夜影院91| 欧美精品一级二级| 国产欧美日韩综合精品一| 亚洲国产精品一区二区久久hs| 日本中文字幕一区| 淫片免费看| 欧美精品日韩| 国产精品99在线播放| 狠狠色狠狠色很很综合很久久| 国产精品黑色丝袜的老师| 精品久久9999| 激情欧美一区二区三区| 欧美国产一区二区在线| 97精品国产aⅴ7777| 国产精品免费自拍| 国产va亚洲va在线va| 日本美女视频一区二区| 色天天综合久久久久综合片| 狠狠插狠狠插| 男女无遮挡xx00动态图120秒| 91一区二区三区视频| 国产偷自视频区视频一区二区| 91精品国产综合久久国产大片| 欧美亚洲另类小说| 国产视频一区二区在线播放| 色就是色欧美亚洲| 欧美精品免费视频| 91精品视频在线免费观看| 日韩欧美激情| 午夜激情影院|